Show simple item record

dc.contributor.authorGammon, Ruperten
dc.contributor.authorFisher, Jillen
dc.contributor.authorIrvine, K. N.en
dc.date.accessioned2017-03-08T16:43:22Z
dc.date.available2017-03-08T16:43:22Z
dc.date.issued2016-09-01
dc.identifier.citationGammon, R., Fisher, J., Irvine, K. N. (2016) Acceptability of Externally Controlled Recharging for the Protection of Local Power Networks with High Penetrations of Electric Vehicles, Advanced Science Letters, 22 (9), pp. 2105-2108en
dc.identifier.urihttp://hdl.handle.net/2086/13485
dc.description.abstractThe anticipated uptake of electric vehicles (EVs) has the potential to overload low-voltage power networks where several EVs might be simultaneously recharging on the same electrical substation feeder. The Esprit system is designed to avoid potential power outages and damage to network infrastructure by means of temporary curtailment of EV recharging to reduce the aggregate load on a single feeder. It is important that this intervention does not adversely affect service quality for EV users and other electricity consumers. In a field trial of localized clusters of EVs, the My Electric Avenue project assessed the acceptability of temporary curtailment of charging to EV drivers as well as testing the technical viability of Esprit. Analysis of data gathered through questionnaires, interviews and focus groups with participants in the trial indicates that temporary curtailment of charging by the Esprit technology did not cause significant inconvenience to EV users.en
dc.language.isoenen
dc.publisherAmerican Scientific Publishersen
dc.subjectControlled Rechargingen
dc.subjectDemand Management;en
dc.subjectElectric Vehiclesen
dc.subjectNetwork Protectionen
dc.subjectUser Acceptanceen
dc.titleAcceptability of Externally Controlled Recharging for the Protection of Local Power Networks with High Penetrations of Electric Vehiclesen
dc.typeArticleen
dc.identifier.doihttps://doi.org/10.1166/asl.2016.7055
dc.researchgroupInstitute of Energy and Sustainable Developmenten
dc.peerreviewedYesen
dc.explorer.multimediaNoen
dc.funderOfgem, Low Carbon Networks Funden
dc.projectidSSET205en
dc.cclicenceN/Aen
dc.date.acceptance2015-09-04en
dc.researchinstituteInstitute of Energy and Sustainable Development (IESD)en
dc.exception.ref2021codes253cen


Files in this item

FilesSizeFormatView

There are no files associated with this item.

This item appears in the following Collection(s)

Show simple item record